Short Notice Sale of an Entire, Large Demountable Building Block of c.4500 SqM
Sale Type:
Private Treaty
Deadlines:
Expressions of Interest by: Wednesday 20 November 2024 Offer Deadline: Friday 29 November 2024
Location:
Blyth, Northumberland
Viewing Information:
Thursday 31 October & Thursday 14 November 2024, Strictly by Prior Appointment
The Joint Liquidators of Power by British Volt Properties Limited
A large demountable building with an estimated total floor area of c.4500 m2, supplied and installed by Portakabin and comprising of two linked sections, each of three storeys, with internal staircases and being largely open plan.
The original built cost (in 2022/3) is understood to have been £5.4 million plus fixtures and fittings.
The HVAC and electrical systems are only partly installed but it appears that much of the hardware is on site, much still in it’s original packaging. In addition, a quantity of furniture is included and further photographs are available.
Subject to availability
Removal
All Lots must be removed before Saturday 1 February 2024, 4:00pm GMT, strictly by prior arrangement
Collection is only permitted once a paid in full invoice has been received
The Buyer and or their removal contractor must supply their own lifting equipment Method statements and risk assessments, copies of all relevant insurances documents and operator licenses must be supplied and approved ahead of any item being dismantled or moved in accordance with Health & Safety policies. Site attendance for the duration of the removal process to be confirmed and agreed in advance
Anyone attending site will be required to wear the relevant PPE workwear including Hi-Viz Vest/Jacket and Safety Footwear.
Terms and Conditions
Buyer’s Premium of 7.5% will be applicable to this sale
VAT at 20% will be added to the total price and Buyer’s Premium. Purchasers from overseas should note that the VAT on the Buyer’s Premium is not recoverable
All payments must be cleared in our account by the date stated on the invoice
All Lots must be removed before Saturday 1 February 2024, 4:00pm GMT
All persons arriving on site must report to the entrance and complete the signing in procedure book
This site is a full PPE area and everyone must comply whilst the site is designated as such. PPE worn must comply with all relevant Method Statements. Anyone not found wearing his/her PPE will be required to leave the site, if in doubt assistance must be sought from the site Supervisor